Dept. of Trans. PROGRESS Serial No. Contract No. 07-171-11-04 07-1199U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 07-LA-101-0.4/0.9 Federal Project: NONE Progress payment No. 36 Payment period ending: 06-20-07 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02188 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,026,182.44 214,662.66 2.a. Extra Work 577,493.78 23,577.65 b. Adjustment Comp. -121,055.89 211.75 3. Materials on Hand 8,043.51 0.00 4. Earned Subject to Retention 12,490,663.84 238,452.06 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 13,782,620.33 7. Deductions -788,972.98 -40,300.00 8. a.Contract Retentions -624,533.19 -11,922.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,377,157.67 186,229.46 10. Reduction Amt to Escrow 11. Payment to Escrow 624,530.00 12. Net Pymt. this Estimate 186,229.46