Dept. of Trans. PROGRESS Serial No. Contract No. 07-264-14-55 07-1199U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-101-0.4/0.9 Federal Project: NONE Progress payment No. 39 Payment period ending: 09-20-07 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02188 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,498,347.09 62,169.00 2.a. Extra Work 696,109.25 29,143.20 b. Adjustment Comp. -121,055.89 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,073,400.45 91,312.20 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 14,373,400.45 7. Deductions -940,272.98 0.00 8. a.Contract Retentions -653,670.02 -4,565.61 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,779,457.45 86,746.59 10. Reduction Amt to Escrow 11. Payment to Escrow 653,670.00 12. Net Pymt. this Estimate 86,746.59