Dept. of Trans. PROGRESS Serial No. Contract No. 07-330-10-54 07-1199U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-101-0.4/0.9 Federal Project: NONE Progress payment No. 41 Payment period ending: 11-20-07 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02188 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,582,863.09 1,336.00 2.a. Extra Work 697,120.26 0.00 b. Adjustment Comp. -82,158.59 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,197,824.76 1,336.00 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 14,497,824.76 7. Deductions -940,272.98 0.00 8. a.Contract Retentions -659,891.24 -66.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,897,660.54 1,269.20 10. Reduction Amt to Escrow 11. Payment to Escrow 659,820.00 12. Net Pymt. this Estimate 1,269.20