Dept. of Trans. PROGRESS Serial No. Contract No. 06-268-06-49 07-120934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 49% 07-LA-710-6.8/R9.4 Federal Project: ACNH-710-1(787) Progress payment No. 04 Payment period ending: 09-20-06 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 349,250.65 206,804.93 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 160,392.76 -44,750.00 4. Earned Subject to Retention 509,643.41 162,054.93 5. Mobilization 161,250.00 0.00 6. Total Work Completed 510,500.65 7. Deductions -61,285.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 609,608.41 162,054.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 162,054.93