Dept. of Trans. PROGRESS Serial No. Contract No. 06-298-08-55 07-120934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 55% 07-LA-710-6.8/R9.4 Federal Project: ACNH-710-1(787) Progress payment No. 05 Payment period ending: 10-20-06 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 609,974.60 260,723.95 2.a. Extra Work 30,131.59 30,131.59 b. Adjustment Comp. 3. Materials on Hand 124,023.55 -36,369.21 4. Earned Subject to Retention 764,129.74 254,486.33 5. Mobilization 204,250.00 43,000.00 6. Total Work Completed 844,356.19 7. Deductions -61,285.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 907,094.74 297,486.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,486.33