Dept. of Trans. PROGRESS Serial No. Contract No. 06-331-09-26 07-120934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 61% 07-LA-710-6.8/R9.4 Federal Project: ACNH-710-1(787) Progress payment No. 07 Payment period ending: 11-20-06 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,095,621.61 485,647.01 2.a. Extra Work 45,861.85 8,460.62 b. Adjustment Comp. 3. Materials on Hand 60,794.55 -63,229.00 4. Earned Subject to Retention 1,202,278.01 430,878.63 5. Mobilization 204,250.00 0.00 6. Total Work Completed 1,345,733.46 7. Deductions -61,285.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,345,243.01 420,878.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 420,878.63