Dept. of Trans. PROGRESS Serial No. Contract No. 07-144-12-06 07-120934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 92% 07-LA-710-6.8/R9.4 Federal Project: ACNH-710-1(787) Progress payment No. 14 Payment period ending: 05-20-07 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,469,907.39 971,961.91 2.a. Extra Work 136,982.83 45,971.08 b. Adjustment Comp. -583,788.75 -583,788.75 3. Materials on Hand 0.00 -44,567.66 4. Earned Subject to Retention 2,023,101.47 389,576.58 5. Mobilization 215,000.00 0.00 6. Total Work Completed 2,238,101.47 7. Deductions -105,985.00 -8,110.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,132,116.47 381,466.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 381,466.58