Dept. of Trans. PROGRESS Serial No. Contract No. 07-171-11-13 07-120934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 98% 07-LA-710-6.8/R9.4 Federal Project: ACNH-710-1(787) Progress payment No. 15 Payment period ending: 06-20-07 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,469,907.39 0.00 2.a. Extra Work 166,680.71 29,697.88 b. Adjustment Comp. -583,788.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,052,799.35 29,697.88 5. Mobilization 215,000.00 0.00 6. Total Work Completed 2,267,799.35 7. Deductions -95,985.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,171,814.35 39,697.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,697.88