Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-215-10-13 07-120934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-710-6.8/R9.4 Federal Project: ACNH-710-1(787) Progress payment No. 16 Payment period ending: 07-19-07 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,489,645.50 19,738.11 2.a. Extra Work 170,932.54 4,251.83 b. Adjustment Comp. -599,310.15 -15,521.40 3. Materials on Hand 4. Earned Subject to Retention 2,061,267.89 8,468.54 5. Mobilization 215,000.00 0.00 6. Total Work Completed 2,276,267.89 7. Deductions -5,000.00 90,985.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,271,267.89 99,453.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,453.54