Dept. of Trans. FINAL Serial No. Contract No. 08-053-12-13 07-120934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-710-6.8/R9.4 Federal Project: ACNH-710-1(787) Progress payment No. 18 Payment period ending: 07-19-07 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,489,645.50 0.00 2.a. Extra Work 170,932.54 0.00 b. Adjustment Comp. -485,259.73 61,562.70 3. Materials on Hand 4. Earned Subject to Retention 2,175,318.31 61,562.70 5. Mobilization 215,000.00 0.00 6. Total Work Completed 2,390,318.31 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,385,318.31 61,562.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,562.70