Dept. of Trans. PROGRESS Serial No. Contract No. 05-203-09-04 07-120974 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 71% 07-LA-57-R0.0/R7.7 Federal Project: ACIM-X037(90) ACNH-X037(90) Progress payment No. 24 Payment period ending: 07-20-05 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 953812968 Escrow No. 02127 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,916,995.86 151,495.61 2.a. Extra Work 1,399,988.29 0.00 b. Adjustment Comp. -13,665.60 0.00 3. Materials on Hand 0.00 -19,045.71 4. Earned Subject to Retention 7,303,318.55 132,449.90 5. Mobilization 260,000.00 0.00 6. Total Work Completed 7,563,318.55 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -365,165.93 -6,622.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,178,152.62 115,827.40 10. Reduction Amt to Escrow 11. Payment to Escrow 365,160.00 12. Net Pymt. this Estimate 115,827.40