Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-060-08-31 07-120974 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-57-R0.0/R7.7 Federal Project: ACIM-X037(90) ACNH-X037(90) Progress payment No. 30 Payment period ending: 01-16-06 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 953812968 Escrow No. 02127 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,267,650.11 59,225.00 2.a. Extra Work 1,620,488.40 13,440.00 b. Adjustment Comp. 9,506.17 -21,837.17 3. Materials on Hand 4. Earned Subject to Retention 7,897,644.68 50,827.83 5. Mobilization 260,000.00 0.00 6. Total Work Completed 8,157,644.68 7. Deductions -30,000.00 32,911.20 8. a.Contract Retentions -381,153.56 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 381,153.56 0.00 9. Total pay to Contractor 8,127,644.68 83,739.03 10. Reduction Amt to Escrow -381,150.00 0.00 11. Payment to Escrow 381,150.00 12. Net Pymt. this Estimate 83,739.03