Dept. of Trans. PROGRESS Serial No. Contract No. 12-331-11-12 07-121844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 49% 07-LA-5-26.7/29.4 Federal Project: CMLN-6207(55) Progress payment No. 24 Payment period ending: 11-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,684,622.70 1,375,998.38 2.a. Extra Work 498,872.58 44,881.34 b. Adjustment Comp. 60,323.88 23,263.62 3. Materials on Hand 1,122,366.05 -103,946.15 4. Earned Subject to Retention 13,366,185.21 1,340,197.19 5. Mobilization 1,330,000.00 0.00 6. Total Work Completed 13,573,819.16 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,696,185.21 1,340,197.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,340,197.19