Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-12-35 07-121844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 86% 07-LA-5-26.7/29.4 Federal Project: CMLN-6207(55) Progress payment No. 57 Payment period ending: 10-20-14 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR, CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,759,921.92 956,063.02 2.a. Extra Work 5,226,151.43 -67,331.87 b. Adjustment Comp. 667,046.01 1,870.18 3. Materials on Hand 1,528,220.10 -20,640.12 4. Earned Subject to Retention 36,181,339.46 869,961.21 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 36,053,119.36 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 37,581,339.46 869,961.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 869,961.21