Dept. of Trans. PROGRESS Serial No. Contract No. 15-236-14-59 07-121844 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 100% Location: Federal Project: 07-LA-5-26.7/29.4 CMLN-6207(55) Progress payment No. 068 Payment period ending: 08-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR, CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,332,429.13 -25,351.76 2. a. Extra Work 6,810,873.72 247,462.41 b. Adustment Comp. 789,028.42 -11,500.00 3. Materials on Hand 758,490.90 -46,591.54 4. Earned Subject to Retention 39,690,822.17 164,019.11 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 40,332,331.27 7. Deductions -114,305.89 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,976,516.28 163,019.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 163,019.11