Dept. of Trans. PROGRESS Serial No. Contract No. 18-082-13-25 07-121844 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 87% Location: Federal Project: 07-LA-5-26.7/29.4 CMLN-6207(55) Progress payment No. 101 Payment period ending: 03-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,782,332.95 27,993.53 2. a. Extra Work 7,910,652.32 0.00 b. Adustment Comp. 7,067,409.66 81,921.53 3. Materials on Hand 853,724.04 99,508.71 4. Earned Subject to Retention 56,614,118.97 209,423.77 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 57,160,394.93 7. Deductions -22,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 57,992,118.97 206,423.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 206,423.77