Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-14-24 07-121844 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 100% Location: Federal Project: 07-LA-5-26.7/29.4 CMLN-6207(55) Progress payment No. 115 Payment period ending: 01-20-19 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,116,495.50 895,845.34 2. a. Extra Work 8,347,938.84 126,765.27 b. Adustment Comp. 28,256,507.09 0.00 3. Materials on Hand 817,059.62 21,673.71 4. Earned Subject to Retention 82,538,001.05 1,044,284.32 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 83,120,941.43 7. Deductions -13,000.00 25,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 83,925,001.05 1,069,284.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,069,284.32