Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 12-125-12-24 07-1218V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 38% 07-LA-5-31.6/36.0 Federal Project: SARR-005-3(29) AL-005-3(29) CMLN-6207(56) Progress payment No. 21 Payment period ending: 04-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,812,225.05 26,988.00 2.a. Extra Work 795,599.52 0.00 b. Adjustment Comp. 300,929.74 0.00 3. Materials on Hand 487,525.00 0.00 4. Earned Subject to Retention 26,396,279.31 26,988.00 5. Mobilization 1,740,000.00 0.00 6. Total Work Completed 27,648,754.31 7. Deductions -20,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,116,279.31 26,988.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,988.00