Dept. of Trans. PROGRESS Serial No. Contract No. 13-023-10-41 07-1218V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 58% 07-LA-5-31.6/36.0 Federal Project: SARR-005-3(29) AL-005-3(29) CMLN-6207(56) Progress payment No. 31 Payment period ending: 01-20-13 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,332,673.14 274,323.17 2.a. Extra Work 1,675,650.69 80,396.82 b. Adjustment Comp. 779,902.89 -2,219.73 3. Materials on Hand 1,030,530.55 -41,403.42 4. Earned Subject to Retention 39,818,757.27 311,096.84 5. Mobilization 1,740,000.00 0.00 6. Total Work Completed 40,528,226.72 7. Deductions -120,000.00 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,438,757.27 291,096.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 291,096.84