Dept. of Trans. PROGRESS Serial No. Contract No. 15-295-12-06 07-1218W4 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 38% Location: Federal Project: 07-LA-5-29.4/31.6 IM-005-3(78) Progress payment No. 043 Payment period ending: 10-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR, CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,179,397.95 3,830,157.44 2. a. Extra Work 11,163,049.87 91,747.05 b. Adustment Comp. 1,831,492.32 884,190.25 3. Materials on Hand 12,234,976.93 1,326,097.16 4. Earned Subject to Retention 65,408,917.07 6,132,191.90 5. Mobilization 6,935,000.00 0.00 6. Total Work Completed 60,108,940.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 72,343,917.07 6,132,191.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,132,191.90