Dept. of Trans. PROGRESS Serial No. Contract No. 18-267-11-54 07-1218W4 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 73% Location: Federal Project: 07-LA-5-29.4/31.6 IM-005-3(78) Progress payment No. 090 Payment period ending: 09-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 103,400,506.58 1,193,564.62 2. a. Extra Work 23,649,878.90 95,051.74 b. Adustment Comp. 6,230,283.16 0.00 3. Materials on Hand 3,601,407.37 -45,633.53 4. Earned Subject to Retention 136,882,076.01 1,242,982.83 5. Mobilization 7,300,000.00 0.00 6. Total Work Completed 140,580,668.64 7. Deductions -26,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 144,156,076.01 1,239,982.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,239,982.83