Dept. of Trans. PROGRESS Serial No. Contract No. 19-266-08-44 07-1218W4 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 73% Location: Federal Project: 07-LA-5-29.4/31.6 IM-005-3(78) Progress payment No. 102 Payment period ending: 09-20-19 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 117,577,418.49 1,153,234.01 2. a. Extra Work 25,889,196.52 145,835.29 b. Adustment Comp. 6,381,553.41 0.00 3. Materials on Hand 3,180,882.94 -28,745.48 4. Earned Subject to Retention 153,029,051.36 1,270,323.82 5. Mobilization 7,300,000.00 0.00 6. Total Work Completed 157,148,168.42 7. Deductions -218,000.00 -100,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 160,111,051.36 1,170,323.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,170,323.82