Dept. of Trans. PROGRESS Serial No. Contract No. 21-141-11-47 07-1218W4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 87% Location: Federal Project: 07-LA-5-29.4/31.6 IM-005-3(78) Progress payment No. 125 Payment period ending: 05-20-21 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 142,928,829.05 2,098,637.30 2. a. Extra Work 44,333,963.02 75,982.61 b. Adustment Comp. 9,116,504.06 0.00 3. Materials on Hand 559,860.34 0.00 4. Earned Subject to Retention 196,939,156.47 2,174,619.91 5. Mobilization 7,300,000.00 0.00 6. Total Work Completed 203,679,296.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 204,239,156.47 2,174,619.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,174,619.91