Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 21-243-16-03 07-1218W4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 82% Location: Federal Project: 07-LA-5-29.4/31.6 IM-005-3(78) Progress payment No. 130 Payment period ending: 08-20-21 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 145,754,912.41 0.00 2. a. Extra Work 45,638,325.13 0.00 b. Adustment Comp. 40,653,801.70 112,086.98 3. Materials on Hand 462,241.00 0.00 4. Earned Subject to Retention 232,509,280.24 112,086.98 5. Mobilization 7,300,000.00 0.00 6. Total Work Completed 239,347,039.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 239,809,280.24 112,086.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 112,086.98