Dept. of Trans. PROGRESS Serial No. Contract No. 22-234-10-05 07-1218W4 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 92% Location: Federal Project: 07-LA-5-29.4/31.6 IM-005-3(78) Progress payment No. 144 Payment period ending: 08-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 152,254,915.78 174,107.05 2. a. Extra Work 50,247,075.05 2,105,179.44 b. Adustment Comp. 42,799,964.73 0.00 3. Materials on Hand 441,341.87 0.00 4. Earned Subject to Retention 245,743,297.43 2,279,286.49 5. Mobilization 7,300,000.00 0.00 6. Total Work Completed 252,601,955.56 7. Deductions -39,890.00 99,187.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 253,003,407.43 2,378,473.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,378,473.49