Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 06-037-11-36 07-122004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 28% 07-LA-5-39.4/45.6 Federal Project: ACNH-005-3(51) I-005-3(51) Progress payment No. 12 Payment period ending: 01-20-06 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE STREET BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,139,008.05 406,094.15 2.a. Extra Work 573,873.44 8,909.19 b. Adjustment Comp. 3. Materials on Hand 674,022.86 0.00 4. Earned Subject to Retention 8,386,904.35 415,003.34 5. Mobilization 3,325,000.00 0.00 6. Total Work Completed 11,037,881.49 7. Deductions -585.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,711,319.35 415,003.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 415,003.34