Dept. of Trans. PROGRESS Serial No. Contract No. 06-235-12-23 07-122004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 50% 07-LA-5-39.4/45.6 Federal Project: ACNH-005-3(51) I-005-3(51) Progress payment No. 20 Payment period ending: 08-20-06 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE STREET BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,400,922.94 1,975,682.75 2.a. Extra Work 887,547.77 12,265.15 b. Adjustment Comp. 285,910.32 0.00 3. Materials on Hand 724,104.72 -210,093.06 4. Earned Subject to Retention 17,298,485.75 1,777,854.84 5. Mobilization 3,325,000.00 0.00 6. Total Work Completed 19,899,381.03 7. Deductions -1,265.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,622,220.75 1,777,854.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,777,854.84