Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-13-28 07-122004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-5-39.4/45.6 Federal Project: ACNH-005-3(51) I-005-3(51) Progress payment No. 28 Payment period ending: 04-20-07 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE STREET BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,243,128.05 912,207.82 2.a. Extra Work 1,471,703.60 33,438.77 b. Adjustment Comp. 334,028.14 0.00 3. Materials on Hand 247,595.40 -293,861.61 4. Earned Subject to Retention 24,296,455.19 651,784.98 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 27,548,859.79 7. Deductions -1,265.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,795,190.19 651,784.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 651,784.98