Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 03-220-13-59 07-1224U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 95% 07-LA-10-42.4/48.3 Federal Project: ACIM-010-1(753) Progress payment No. 32 Payment period ending: 07-20-03 BALFOUR BEATTY ORTIZ ENTERPRISES INC 1255 E.HIGHLAND AVE STE,212 SAN BERNARDINO CA 92404 Escrow No. 01699 Total Estimate This Estimate 1. Contract Itms Without Mobil. 58,708,938.92 9,000.00 2.a. Extra Work 6,748,853.95 0.00 b. Adjustment Comp. 1,898,112.30 0.00 3. Materials on Hand 217,130.88 0.00 4. Earned Subject to Retention 67,573,036.05 9,000.00 5. Mobilization 7,500,000.00 0.00 6. Total Work Completed 74,855,905.17 7. Deductions -86,566.87 0.00 8. a.Contract Retentions -3,378,651.80 -450.00 b. Unsatisfactory Prog. 0.00 107,841.63 c. Reduction after 95% Comp. 9. Total pay to Contractor 71,607,817.38 116,391.63 10. Reduction Amt to Escrow 11. Payment to Escrow 3,378,650.00 12. Net Pymt. this Estimate 116,391.63