Dept. of Trans. PROGRESS Serial No. Contract No. 04-056-11-43 07-1224U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 07-LA-10-42.4/48.3 Federal Project: ACIM-010-1(753) Progress payment No. 39 Payment period ending: 02-20-04 BALFOUR BEATTY CONSTRUCTION, INC. WESTERN DIVISION ONE HARBOR CENTER,SUITE 350 SUISUN CITY, CA 94585 Escrow No. 01699 Total Estimate This Estimate 1. Contract Itms Without Mobil. 66,346,037.95 -49,306.55 2.a. Extra Work 7,406,995.19 305,350.64 b. Adjustment Comp. 2,341,557.22 40,960.40 3. Materials on Hand 126,405.32 -173,795.27 4. Earned Subject to Retention 76,220,995.68 123,209.22 5. Mobilization 7,500,000.00 0.00 6. Total Work Completed 83,594,590.36 7. Deductions -65,612.87 0.00 8. a.Contract Retentions -3,811,049.78 -6,160.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 79,844,333.03 117,048.76 10. Reduction Amt to Escrow 11. Payment to Escrow 3,811,040.00 12. Net Pymt. this Estimate 117,048.76