Dept. of Trans. PROGRESS Serial No. Contract No. 04-023-16-27 07-1257U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 22% 07-LA-60-R22.4/R25.0 Federal Project: ACST-X037(114) P-X037(114) Progress payment No. 09 Payment period ending: 01-20-04 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 02084 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,475,477.26 1,141,448.46 2.a. Extra Work 193,825.12 4,559.90 b. Adjustment Comp. -51.32 0.00 3. Materials on Hand 418,481.33 -18,960.48 4. Earned Subject to Retention 7,087,732.39 1,127,047.88 5. Mobilization 3,518,250.00 0.00 6. Total Work Completed 10,187,501.06 7. Deductions -63,000.00 0.00 8. a.Contract Retentions -708,773.24 -112,704.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,834,209.15 1,014,343.09 10. Reduction Amt to Escrow 11. Payment to Escrow 708,770.00 12. Net Pymt. this Estimate 1,014,343.09