Dept. of Trans. PROGRESS Serial No. Contract No. 06-025-08-35 07-1257U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 76% 07-LA-60-R22.4/R25.0 Federal Project: ACST-X037(114) P-X037(114) Progress payment No. 35 Payment period ending: 01-20-06 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 02084 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,667,292.29 552,003.00 2.a. Extra Work 1,802,147.83 587,081.88 b. Adjustment Comp. 635,016.68 167,303.57 3. Materials on Hand 204,782.87 -376,849.53 4. Earned Subject to Retention 37,309,239.67 929,538.92 5. Mobilization 4,691,000.00 0.00 6. Total Work Completed 41,795,456.80 7. Deductions -223,280.86 -10,000.00 8. a.Contract Retentions -1,865,461.98 -46,476.94 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,911,496.83 873,061.98 10. Reduction Amt to Escrow 11. Payment to Escrow 1,865,460.00 12. Net Pymt. this Estimate 873,061.98