Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-14-00 07-1257U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-60-R22.4/R25.0 Federal Project: ACST-X037(114) P-X037(114) Progress payment No. 52 Payment period ending: 04-20-07 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 02084 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,856,737.45 317,495.25 2.a. Extra Work 4,911,630.87 72,449.28 b. Adjustment Comp. 859,625.60 0.00 3. Materials on Hand 18,570.27 -140.08 4. Earned Subject to Retention 52,646,564.19 389,804.45 5. Mobilization 4,691,000.00 0.00 6. Total Work Completed 57,318,993.92 7. Deductions -231,679.77 0.00 8. a.Contract Retentions -2,632,328.21 -19,490.22 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 54,473,556.21 370,314.23 10. Reduction Amt to Escrow 11. Payment to Escrow 2,632,320.00 12. Net Pymt. this Estimate 370,314.23