Dept. of Trans. PROGRESS Serial No. Contract No. 06-116-09-16 07-1264F4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 15% 07-LA-210-R49.3/R52.1 Federal Project: NONE Progress payment No. 09 Payment period ending: 04-20-06 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02205 Total Estimate This Estimate 1. Contract Itms Without Mobil. 674,862.30 150,398.05 2.a. Extra Work b. Adjustment Comp. 58,826.34 0.00 3. Materials on Hand 4. Earned Subject to Retention 733,688.64 150,398.05 5. Mobilization 128,250.00 0.00 6. Total Work Completed 861,938.64 7. Deductions 8. a.Contract Retentions -36,684.43 -3,618.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 825,254.21 146,779.88 10. Reduction Amt to Escrow 11. Payment to Escrow 36,680.00 12. Net Pymt. this Estimate 146,779.88