Dept. of Trans. PROGRESS Serial No. Contract No. 08-298-13-08 07-127214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 34% 07-LA-138-51.9/52.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,117,806.43 1,174,019.36 2.a. Extra Work b. Adjustment Comp. -7,311.02 -8,432.80 3. Materials on Hand 4. Earned Subject to Retention 2,110,495.41 1,165,586.56 5. Mobilization 101,240.55 0.00 6. Total Work Completed 2,211,735.96 7. Deductions 8. a.Contract Retentions -105,524.77 -14,841.07 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,106,211.19 1,150,745.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,150,745.49