Dept. of Trans. PROGRESS Serial No. Contract No. 08-359-08-12 07-127214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 56% 07-LA-138-51.9/52.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 12-20-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,206,096.15 1,092,925.28 2.a. Extra Work b. Adjustment Comp. -61,469.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,144,626.40 1,092,925.28 5. Mobilization 106,569.00 0.00 6. Total Work Completed 4,251,195.40 7. Deductions 8. a.Contract Retentions -207,231.32 -54,646.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,043,964.08 1,038,279.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,038,279.02