Dept. of Trans. PROGRESS Serial No. Contract No. 09-167-11-57 07-127214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 98% 07-LA-138-51.9/52.5 Federal Project: NONE Progress payment No. 06 Payment period ending: 06-20-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,308,067.75 101,971.60 2.a. Extra Work 443.56 443.56 b. Adjustment Comp. -82,387.26 -20,917.51 3. Materials on Hand 4. Earned Subject to Retention 4,226,124.05 81,497.65 5. Mobilization 106,569.00 0.00 6. Total Work Completed 4,332,693.05 7. Deductions 8. a.Contract Retentions -211,306.20 -4,074.88 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,121,386.85 77,422.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,422.77