Dept. of Trans. PROGRESS Serial No. Contract No. 08-205-10-09 07-127234 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 13% 07-LA-138-56.2/57.2 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 750,774.00 433,840.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 750,774.00 433,840.00 5. Mobilization 199,973.25 66,657.75 6. Total Work Completed 950,747.25 7. Deductions 8. a.Contract Retentions -75,077.40 -43,384.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 875,669.85 457,113.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 457,113.75