Dept. of Trans. FINAL Serial No. Contract No. 13-177-11-46 07-1294V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-60-11.8/23.3 Federal Project: ACNH-P060(130) CMLN-6207(40) Progress payment No. 52 Payment period ending: 04-12-11 COOPER ENGINEERING INC 281 CORPORATE TERRACE CORONA CA 92879 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 104,253,478.61 0.00 2.a. Extra Work 3,381,259.39 0.00 b. Adjustment Comp. 1,483,277.95 81,999.00 3. Materials on Hand 4. Earned Subject to Retention 109,118,015.95 81,999.00 5. Mobilization 10,050,000.00 0.00 6. Total Work Completed 119,168,015.95 7. Deductions -39,237.80 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 119,128,778.15 81,999.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,999.00