Dept. of Trans. PROGRESS Serial No. Contract No. 05-298-06-40 07-135104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 92% 07-LA-10-S0.0/S1.0 Federal Project: ACST-010-1(777) PHG-010-1(777) Progress payment No. 09 Payment period ending: 10-20-05 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 766,754.69 200,868.00 2.a. Extra Work 12,498.06 2,606.20 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 779,252.75 203,474.20 5. Mobilization 171,000.00 0.00 6. Total Work Completed 950,252.75 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. -41,076.32 -20,347.42 c. Reduction after 95% Comp. 9. Total pay to Contractor 899,176.43 173,126.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,126.78