Dept. of Trans. PROGRESS Serial No. Contract No. 12-024-08-33 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 3% 07-LA-47-3.4/4.6 Federal Project: NHBR-P047(10) Progress payment No. 05 Payment period ending: 01-20-12 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,782,909.26 952,575.26 2.a. Extra Work 60,000.00 0.00 b. Adjustment Comp. 15,995.76 -3,651.06 3. Materials on Hand 2,228,535.07 1,636,555.07 4. Earned Subject to Retention 6,087,440.09 2,585,479.27 5. Mobilization 6. Total Work Completed 3,858,905.02 7. Deductions -15,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,072,440.09 2,575,479.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,575,479.27