Dept. of Trans. PROGRESS Serial No. Contract No. 12-114-15-25 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 7% 07-LA-47-3.4/4.6 Federal Project: NHBR-P047(10) Progress payment No. 08 Payment period ending: 04-20-12 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,517,068.51 1,293,859.11 2.a. Extra Work 157,481.70 80,759.31 b. Adjustment Comp. 15,500.26 -7,044.44 3. Materials on Hand 3,524,632.15 573,514.72 4. Earned Subject to Retention 11,214,682.62 1,941,088.70 5. Mobilization 9,464,678.50 0.00 6. Total Work Completed 17,154,728.97 7. Deductions -451,678.52 30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,227,682.60 1,971,088.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,971,088.70