Dept. of Trans. PROGRESS Serial No. Contract No. 12-205-10-08 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 11% 07-LA-47-3.4/4.6 Federal Project: NHBR-P047(10) Progress payment No. 12 Payment period ending: 07-20-12 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,978,387.09 933,822.49 2.a. Extra Work 386,000.72 4,493.07 b. Adjustment Comp. -90,454.82 -119,755.43 3. Materials on Hand 4,357,502.38 41,539.46 4. Earned Subject to Retention 14,631,435.37 860,099.59 5. Mobilization 14,197,017.75 0.00 6. Total Work Completed 24,470,950.74 7. Deductions -5,191,017.77 -7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,637,435.35 853,099.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 853,099.59