Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-12-14 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 13% 07-LA-47-3.4/4.6 Federal Project: NHBR-P047(10) Progress payment No. 13 Payment period ending: 08-20-12 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,123,135.09 1,144,748.00 2.a. Extra Work 464,719.67 78,718.95 b. Adjustment Comp. -88,454.82 2,000.00 3. Materials on Hand 4,156,426.04 -201,076.34 4. Earned Subject to Retention 15,655,825.98 1,024,390.61 5. Mobilization 14,197,017.75 0.00 6. Total Work Completed 25,696,417.69 7. Deductions -5,196,017.77 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,656,825.96 1,019,390.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,019,390.61