Dept. of Trans. PROGRESS Serial No. Contract No. 13-113-11-11 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 23% 07-LA-47-3.4/4.6 Federal Project: NHBR-P047(10) Progress payment No. 19 Payment period ending: 04-20-13 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,989,392.11 826,846.32 2.a. Extra Work 1,477,351.81 207,395.06 b. Adjustment Comp. -6,782.40 0.00 3. Materials on Hand 10,013,573.09 659,049.09 4. Earned Subject to Retention 34,473,534.61 1,693,290.47 5. Mobilization 17,982,889.15 0.00 6. Total Work Completed 42,442,850.67 7. Deductions -875,159.18 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 51,581,264.58 1,693,290.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,693,290.47