Dept. of Trans. PROGRESS Serial No. Contract No. 13-164-14-21 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 25% 07-LA-47-3.4/4.6 Federal Project: NHBR-P047(10) Progress payment No. 21 Payment period ending: 06-20-13 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,888,877.91 1,697,583.75 2.a. Extra Work 1,543,308.12 0.00 b. Adjustment Comp. -6,782.40 0.00 3. Materials on Hand 11,245,716.77 1,041,638.82 4. Earned Subject to Retention 38,671,120.40 2,739,222.57 5. Mobilization 17,982,889.15 0.00 6. Total Work Completed 45,408,292.78 7. Deductions -880,484.18 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 55,773,525.37 2,739,222.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,739,222.57