Dept. of Trans. PROGRESS Serial No. Contract No. 15-173-13-44 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 59% Location: Federal Project: 07-LA-47-3.4/4.6 NHBR-P047(10) Progress payment No. 039 Payment period ending: 06-20-15 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 70,476,642.45 1,419,041.34 2. a. Extra Work 5,598,095.68 58,886.97 b. Adustment Comp. 2,252,275.76 -23,073.76 3. Materials on Hand 12,985,067.45 -83,194.34 4. Earned Subject to Retention 91,312,081.34 1,371,660.21 5. Mobilization 18,929,357.00 0.00 6. Total Work Completed 97,256,370.89 7. Deductions -977,644.72 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 109,263,793.62 1,371,660.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,371,660.21