Dept. of Trans. PROGRESS Serial No. Contract No. 15-327-07-02 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 68% Location: Federal Project: 07-LA-47-3.4/4.6 NHBR-P047(10) Progress payment No. 045 Payment period ending: 11-20-15 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,273,545.01 248,497.50 2. a. Extra Work 7,789,748.95 1,348,614.12 b. Adustment Comp. 2,197,061.66 -109,497.32 3. Materials on Hand 12,513,069.05 -31,521.81 4. Earned Subject to Retention 97,773,424.67 1,456,092.49 5. Mobilization 18,929,357.00 0.00 6. Total Work Completed 104,189,712.62 7. Deductions -977,644.72 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 115,725,136.95 1,456,092.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,456,092.49