Dept. of Trans. PROGRESS Serial No. Contract No. 18-054-16-27 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 77% Location: Federal Project: 07-LA-47-3.4/4.6 NHBR-P047(10) Progress payment No. 074 Payment period ending: 02-20-18 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 112,601,373.27 186,118.20 2. a. Extra Work 62,266,387.87 468,283.81 b. Adustment Comp. 13,892,645.47 136,901.81 3. Materials on Hand 7,074,676.76 204,670.37 4. Earned Subject to Retention 195,835,083.37 995,974.19 5. Mobilization 18,929,357.00 0.00 6. Total Work Completed 207,689,763.61 7. Deductions -1,100,603.32 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 213,663,837.05 995,974.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 995,974.19