Dept. of Trans. PROGRESS Serial No. Contract No. 20-112-17-28 07-138204 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 83% Location: Federal Project: 07-LA-47-3.4/4.6 NHBR-P047(10) Progress payment No. 103 Payment period ending: 04-20-20 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 138,763,017.30 488,800.00 2. a. Extra Work 136,861,181.23 0.00 b. Adustment Comp. 62,077,756.13 0.00 3. Materials on Hand 1,060,641.82 -96,456.28 4. Earned Subject to Retention 338,762,596.48 392,343.72 5. Mobilization 18,929,357.00 0.00 6. Total Work Completed 356,631,311.66 7. Deductions -6,828,435.32 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 350,863,518.16 392,343.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 392,343.72